• Erection, Installation, Testing, Commissioning and handover of Two units of HRSG of 750 MW Sabiya CCGT-3 Project at Alghanim International General Trading & Contracting Co. W.L.L, Sabiya, Kuwait on 20th Nov 2018
  • Work of Superstructure Civil, Structural and Architectural Works of Package-1, Main Plant Area of Unit 1 at 2x800 MW at BHEL, Uppur Super Critical Thermal Power Project, Ramanathapuram, Tamil Nadu, India on 19th Nov 2018
  • Pre-Assembly, Erection, Testing and Commissioning of Power Cycle Piping, LP Piping for Power Cycle and all associated piping of 1 X 800 MW, Stage–V for  NTTPS, Vijayawada, Andhra Pradesh, India on 29th Oct 2018
  • Fabrication, Supply, Erection and alignment of Pre-Fabricated Steel Structure for Pellet Plant # 2, Package # 4 project at JSW Dolvi, Raigad, Mumbai, India on 10th Oct 2018
  • Civil, Structural and Architectural works of Unit # 1& 2 for 2 X 660 MW Maitree Rampal Project Package 10A-MP U#1&2 of BHEL,  Maitree, Bangladesh on 17th Sep 2018
  • Design, Fabrication, Supply, Erection and Alignment of Prefabricated steel structure for Power Plant- II(60 MW & 175 MW) project of JSW Steel Limited at JSW Dolvi, Maharashtra, India on 01st Sep 2018
  • Erection, Testing & Commissioning Works of 225 MW Bhola Combined Cycle Power Project of Bisho Infra Projects Ltd, Bhola, Bangladesh on 21st Aug 2018
  • APSSA - Civil Works - "Package-l Providing necessary infrastructure viz. Furniture and Additional Class Rooms including Library Rooms & Electrical facilities in all Government Schools, KGBVs & Bhavitha Buildings of APSSA at Srikakulam, Vizianagaram and Visakhapatnam Districts, Andhra Pradesh, India on 30th Jun 2018
  • APSSA - Civil Works - "Package-ll Providing necessary infrastructures viz. Furniture and  Additional Class Rooms including Library Rooms & Electrical facilities in all Government Schools, KGBVs & Bhavitha Buildings of APSSA at Krishna and Guntur Districts, Andhra Pradesh, India on 30th Jun 2018
  • Installation of FGD & SCR at 1X660 MW Harduaganj Thermal Power Plant of Doosan Power Systems India Pvt Ltd,  Harduaganj, Uttar Pradesh, India on 30th Jun 2018

  • Construction of Ramayampet Canal of Kaleshwaram Project including distributory network for irrigating an ayacut of 41203 Acres for Telanga Government, Siddipet, Telangana, India on 14th Jun 2018
  • ETC of 1X660 MW Boiler & Auxiliaries of Unit-1 including Auxiliary Boiler, O&M for supply of Cranes and providing FSA Engineers for BHEL, Maitree STPP, Rampal, Bangladesh  on 4th May 2018
  • Services of Onsite Mechanical Assembly of 1390 MW Steam Turbine for ABENER, Waad Al Shamal ISCC Power Plant, KSA on 3rd May 2018
  • Mechanical Assembly for the  Shuaibah-3 Second Water Expansion Seawater Desalination Plant of Fisia Abeima LLC, Shuaibah, KSA  30th Apr 2018

  • Dismantling and Erection of Pressure parts in Stage -1 of 3X660 MW NTPC Barh, Bihar, India on 27th March 2018
  • Laying of 16” OD  22.5 Km R-LNG Pipe line from Ennore LNG M terminal to MFL of EMBPL, Tamilnadu, India on  30th Jan 2018
  • Erection, Installation, Testing and Commissioning and handover of Two Units of HRSG of 750 MW Sabiya CCGT-1 Project, Kuwait on 24th Jan 2018

Site: 2x660 MW Solapur STPP, Solapur, Maharashtra, India

Client: NTPC

Milestone

a)      Steam Blowing Successfully started  on 30th December 2018

 

Site: 1800 MW ALBA Line 6 Expansion, Power Station 5 CCP Project, Bahrain   

Client: Gama Power Systems Engineering & Contracting Inc.

Milestone

a) HRSG#3 HP System Hydraulic Test Successfully Completed on 18th December 2018

b) Gas Turbine#2 First Fire Successfully Completed on 26th December 2018

 

Site: 2 X 600 MW , U#7, SCTPP of Suratgarh,  Rajasthan, India

Client: BHEL

 Milestone

 a) Synchronization & Coal Firing successfully completed on dated: 18.12.2018

 

Site: 750 MW Sabiya CCGT-1 Project, Kuwait   

Client: Alghanim International General Trading & Contracting Co. W.L.L

Milestone

a) HRSG#1 Hydraulic Test Successfully Completed on 17th December 2018

 

Site: 1519 MW Fadhili CHPP, Kingdom of Saudi Arabia

Client: Doosan Heavy Industries & Construction Co. Ltd.,

Milestone

a) Received an Award from M/s. FPCC for Achievement of "Early Steam Operation Date" as per targeted timeline on 17th December 2018

 

Site: 1516 MW IBRI Independent Power Project, OMAN

Client: TIEJUN IBRI Power Construction L.L.C (Sepco-III)

Milestone

a) Steam Blowing Successfully Completed on 11th December 2018

 

Site: U#2 at 2X500MW –Neyveli, Tamil Nadu, India    

Client: Neyveli New Thermal Power Station 

Milestone

a) HYDRO TEST Completed for Unit#2  on 26.11.2018    

 

Site:  Maitree, STPP 2 X 660MW, Rampal, Bangladesh

Client: BHEL

Milestone

a) Erection work in Main Power House (Package-10A) on 18.11.2018    

 

Site:  Solapur Unit#2 at 2X660 MW Solpaur STPP, Maharashtra, India

Client: NTPC

Milestone

a)  Boiler Light Up on 18.11.2018    

 

Site: 1800 MW ALBA Line 6 Expansion, Power Station 5 CCP Project, Bahrain    

Client: Gama Power Systems Engineering & Contracting Inc. 

Milestone

a) GT#1 Fire Successfully Completed on 30.10.2018

 

Site: 1516 MW IBRI Independent Power Project, OMAN 

Client: TIEJUN IBRI Power Construction L.L.C (Sepco-III)

Milestone

a) GT#11 First Fire Successfully Completed with Fuel Gas @ 3000 RPM on 11.10.2018

b) GT#12 First Fire Successfully Completed with Fuel Gas @ 3000 RPM on 16.10.2018

 

Site : 2X660MW –SCTPP, Suratgarh, Rajasthan, India

Client : BHEL

Boiler chemical cleaning of U#8 at 2X660MW on 08.10.2018

 

Site: 1519 MW Fadhili CHPP, Kingdom of Saudi Arabia

Client: Doosan Heavy Industries & Construction Co. Ltd.,

Milestone

a) Reserve Boiler First Fire Completed on 29.09.2018

 

Site: 1800 MW ALBA Line 6 Expansion, Power Station 5 CCP Project, Bahrain    

Client: Gama Power Systems Engineering & Contracting Inc. 

Milestone

a) HRSG#2 LP System Hydraulic Test Completed on 25.09.2018.

 

Site : U#2 of 3X660MW of Nabinagar, STPP, Bihar, India

Client: Nabinagar Power Generating Company Limited

Milestone

a) TG Barring  Gear of Turbine of U#2 at 3X660MW Completed on 21.09.2018

 

Site: Unit#2 at 2X660 MW Solpaur STPP, Solapur, Maharashtra, India

Client: NTPC

Milestone

a)  HYDRO TEST Completed for Boiler of Unit#2  on 31.08.2018

 

Site: 1516 MW IBRI Independent Power Project, OMAN

Client: TIEJUN IBRI Power Construction L.L.C (Sepco-III)

Milestone

a) STG HP System - Hydraulic test completed on 27.08.2018

 

Site : 2X660MW –SCTPP, Suratgarh, Rajasthan, India

Client : BHEL

a) Steam Blowing of U#8 at 2X660MW on dated: 25.08.2018

 

Site: 750 MW Sabiya CCGT-1 Project, Kuwait   

Client: Alghanim International General Trading & Contracting Co. W.L.L

Milestone

a) HRSG#2 Modules erection Completed on 01.08.2018

b)  HRSG#1 Stack lifting completed on 08.08.2018

c) HRSG#2 HP & IP Drum erection Completed on 14.08.2018

d) HRSG#2 LP Drum erection Completed on 24.08.2018

 

Site: 1519 MW Fadhili CHPP, Kingdom of Saudi Arabia

Client: Doosan Heavy Industries & Construction Co. Ltd.,

Milestone

a) Reserve Boiler Hydraulic Test Completed on 04.08.2018

 

Site: 1516 MW IBRI Independent Power Project, OMAN 

Client: TIEJUN IBRI Power Construction L.L.C (Sepco-III)

Milestone

a) STG Auxiliary System - HTP-1 Hydraulic test completed on 29.08.2018

 

Site: 2X660MW – Suratgarh, SCTPP, Rajasthan, India

Client: BHEL

Milestone

a) Boiler Non Drainable Hydro Test” of U#8  completed on 27.07.2018

 

Site: 2X360MW – Barh, STPP, Barh, Bihar, India

Client: BHEL

Milestone

a) Hydro Test of U#2 completed on 24.07.2018

 

Site: 1519 MW Fadhili CHPP, Kingdom of Saudi Arabia

Client: Doosan Heavy Industries & Construction Co. Ltd.,

Milestone

a) STG#2 ILP Turbine placement on 12.07.2018

b) STG#2 HP Turbine placement on 15.07.2018

c) STG#2 Generator placement on 17.07.2018

 

Site: 750 MW Sabiya CCGT-1 Project, Kuwait    

Client: Alghanim International General Trading & Contracting Co. W.L.L

Milestone

a) HRSG#1 HP Drum lifting completed on 04.07.2018 

b) HRSG#1 IP & LP Drums lifting completed on 12.07.2018

b) HRSG#2 Modules erection Started on 07.07.2018.

 

Power Mech Projects Limited was listed with BSE and NSE. The listing ceremony was held at BSE with striking of the Gong by CMD Mr.S.Kishore Babu.