Mile Stones

Site:  Solapur Unit#2 at 2X660 MW Solpaur STPP, Maharashtra, India

Client: NTPC

Milestone

a)  Boiler Light Up on 18.11.2018    

 

 Site: U#2 at 2X500MW –Neyveli, Tamil Nadu, India    

Client: Neyveli New Thermal Power Station 

Milestone

a) HYDRO TEST Completed for Unit#2  on 26.11.2018    

 

Site:  Maitree, STPP 2 X 660MW, Rampal, Bangladesh

Client: BHEL

Milestone

a) Erection work in Main Power House (Package-10A) on 18.11.2018    

 

Site: 1800 MW ALBA Line 6 Expansion, Power Station 5 CCP Project, Bahrain    

Client: Gama Power Systems Engineering & Contracting Inc. 

Milestone

a) GT#1 Fire Successfully Completed on 30.10.2018

 

Site: 1516 MW IBRI Independent Power Project, OMAN 

Client: TIEJUN IBRI Power Construction L.L.C (Sepco-III)

Milestone

a) GT#11 First Fire Successfully Completed with Fuel Gas @ 3000 RPM on 11.10.2018

b) GT#12 First Fire Successfully Completed with Fuel Gas @ 3000 RPM on 16.10.2018

 

Site : 2X660MW –SCTPP, Suratgarh, Rajasthan, India

Client : BHEL

Boiler chemical cleaning of U#8 at 2X660MW on 08.10.2018

 

Site: 1519 MW Fadhili CHPP, Kingdom of Saudi Arabia

Client: Doosan Heavy Industries & Construction Co. Ltd.,

Milestone

a) Reserve Boiler First Fire Completed on 29.09.2018

 

Site: 1800 MW ALBA Line 6 Expansion, Power Station 5 CCP Project, Bahrain    

Client: Gama Power Systems Engineering & Contracting Inc. 

Milestone

a) HRSG#2 LP System Hydraulic Test Completed on 25.09.2018.

 

Site : U#2 of 3X660MW of Nabinagar, STPP, Bihar, India

Client: Nabinagar Power Generating Company Limited

Milestone

a) TG Barring  Gear of Turbine of U#2 at 3X660MW Completed on 21.09.2018

 

Site: Unit#2 at 2X660 MW Solpaur STPP, Solapur, Maharashtra, India

Client: NTPC

Milestone

a)  HYDRO TEST Completed for Boiler of Unit#2  on 31.08.2018

 

Site: 1516 MW IBRI Independent Power Project, OMAN

Client: TIEJUN IBRI Power Construction L.L.C (Sepco-III)

Milestone

a) STG HP System - Hydraulic test completed on 27.08.2018

 

Site : 2X660MW –SCTPP, Suratgarh, Rajasthan, India

Client : BHEL

a) Steam Blowing of U#8 at 2X660MW on dated: 25.08.2018

 

Site: 750 MW Sabiya CCGT-1 Project, Kuwait   

Client: Alghanim International General Trading & Contracting Co. W.L.L

Milestone

a) HRSG#2 Modules erection Completed on 01.08.2018

b)  HRSG#1 Stack lifting completed on 08.08.2018

c) HRSG#2 HP & IP Drum erection Completed on 14.08.2018

d) HRSG#2 LP Drum erection Completed on 24.08.2018

 

Site: 1519 MW Fadhili CHPP, Kingdom of Saudi Arabia

Client: Doosan Heavy Industries & Construction Co. Ltd.,

Milestone

a) Reserve Boiler Hydraulic Test Completed on 04.08.2018

 

Site: 1516 MW IBRI Independent Power Project, OMAN 

Client: TIEJUN IBRI Power Construction L.L.C (Sepco-III)

Milestone

a) STG Auxiliary System - HTP-1 Hydraulic test completed on 29.08.2018

 

Site: 2X660MW – Suratgarh, SCTPP, Rajasthan, India

Client: BHEL

Milestone

a) Boiler Non Drainable Hydro Test” of U#8  completed on 27.07.2018

 

Site: 2X360MW – Barh, STPP, Barh, Bihar, India

Client: BHEL

Milestone

a) Hydro Test of U#2 completed on 24.07.2018

 

Site: 1519 MW Fadhili CHPP, Kingdom of Saudi Arabia

Client: Doosan Heavy Industries & Construction Co. Ltd.,

Milestone

a) STG#2 ILP Turbine placement on 12.07.2018

b) STG#2 HP Turbine placement on 15.07.2018

c) STG#2 Generator placement on 17.07.2018

 

Site: 750 MW Sabiya CCGT-1 Project, Kuwait    

Client: Alghanim International General Trading & Contracting Co. W.L.L

Milestone

a) HRSG#1 HP Drum lifting completed on 04.07.2018 

b) HRSG#1 IP & LP Drums lifting completed on 12.07.2018

b) HRSG#2 Modules erection Started on 07.07.2018.

 

Site: MAITREE STPP 2 X 660 MW Rampal, Bangladesh

Client:  BHEL

Mile Stone

Successfully Started Erection of U#1 Boiler on 30.06.2018

 

 

Site: 750 MW Sabiya CCGT-1 Project, Kuwait   

Client: Alghanim International General Trading & Contracting Co. W.L.L

Milestone

HRSG#11 Modules erection Completed on 29.06.2018.

 

Site: 1516 MW IBRI Independent Power Project, OMAN

Client: TIEJUN IBRI Power Construction L.L.C (Sepco-III)

Milestone

HRSG#2 - HTP-1,2,3,4,5 & 6 Hydraulic test completed on 25.06.2018

 

Site: 1519 MW Fadhili CHPP, Kingdom of Saudi Arabia

Client: Doosan Heavy Industries & Construction Co. Ltd.

Milestone

a) GTG#4 Gas Turbine on foundation by 12.06.2018.

b) GTG#4 Gas Turbine Generator on foundation by 14.06.2018.

 