Mile Stones

Site: U#2 at 2X600MW –Solapur, STPP, Maharashtra, India

Client: NTPC

Milestone 

a) Synchronization Successfully Completed on 15th Feb 2019.

 

Site: 1519 MW Fadhili CHPP, Kingdom of Saudi Arabia  

Client: Doosan Heavy Industries & Construction Co. Ltd.,

Milestone 

a) Gas Turbine Generator#1 First Fire Successfully Completed on 5th February 2019.

b) Gas Turbine Generator#2 First Fire Successfully Completed on 10th February 2019.

c) Steam Turbine  Generator#1 Steam Blowing Successfully Started on 12th February 2019.


 

Site: 1800 MW ALBA Line 6 Expansion, Power Station 5 CCP Project, Bahrain    

Client: Gama Power Systems Engineering & Contracting Inc. 

Milestone

a) HRSG#3 LP System Hydraulic Test Successfully Completed on 9th February 2019.

 

Site: 750 MW Sabiya CCGT-1 Project, Kuwait

Client: Alghanim International General Trading & Contracting Co. W.L.L.

Milestone

a)  HRSG # 12  Hydraulic Test Successfully Completed on 24th January 2019.

 

Site: 1516 MW IBRI Independent Power Project, OMAN  

Client: TIEJUN IBRI Power Construction L.L.C (Sepco-III)

Milestone

a) Block-10 STG successfully Synchronized and Achieved full Load of 288 MW on 23rd January 2019.

 

Site: 2x660 MW Solapur STPP, Solapur, Maharashtra, India

Client: NTPC

Milestone

a)      Steam Blowing Successfully started  on 30th December 2018

 

Site: 1800 MW ALBA Line 6 Expansion, Power Station 5 CCP Project, Bahrain   

Client: Gama Power Systems Engineering & Contracting Inc.

Milestone

a) HRSG#3 HP System Hydraulic Test Successfully Completed on 18th December 2018

b) Gas Turbine#2 First Fire Successfully Completed on 26th December 2018

 

Site: 2 X 600 MW , U#7, SCTPP of Suratgarh,  Rajasthan, India

Client: BHEL

 Milestone

 a) Synchronization & Coal Firing successfully completed on dated: 18.12.2018

 

Site: 750 MW Sabiya CCGT-1 Project, Kuwait   

Client: Alghanim International General Trading & Contracting Co. W.L.L

Milestone

a) HRSG#1 Hydraulic Test Successfully Completed on 17th December 2018

 

Site: 1519 MW Fadhili CHPP, Kingdom of Saudi Arabia

Client: Doosan Heavy Industries & Construction Co. Ltd.,

Milestone

a) Received an Award from M/s. FPCC for Achievement of "Early Steam Operation Date" as per targeted timeline on 17th December 2018

 

Site: 1516 MW IBRI Independent Power Project, OMAN

Client: TIEJUN IBRI Power Construction L.L.C (Sepco-III)

Milestone

a) Steam Blowing Successfully Completed on 11th December 2018

 