Mile Stones

1800 MW ALBA Line 6 Expansion, Power Station 5 CCP Project,

Gama Power Systems Engineering & Contracting Inc. , Bahrain    

    A) HRSG#1 LP, IP Drums Successfully Completed on 30th Oct'2017

    B) HRSG#1 HP Drum Lifting Successfully Completed on 28th Oct'2017

    C) HRSG#3 1st Column Erection on 26th Oct'2017

    D) GTG#1 Rotor Insertion successfully Completed on 26th Oct'17

    E) HRSG#1 1st Module Erection Successfully Completed on 16th Oct'2017

Successfully Completed Boiler Light up 660MW Unit #8 of RRVUNL at Suratgarh, Rajasthan on 28th Sep 2017

    A) HRSG#1 1st Module Erection Successfully Started on 20th Sep'2017

    B) Center line Package-Exhaust Duct Successfully Started on 14th Sep'2017. 

        1800 MW ALBA Line 6 Expansion, Power Station 5 CCP Project at Gama Power Systems 

        Engineering  & Contracting Inc.

Successfully Started HRSG#2 First Column Erection of 1800 MW ALBA Line 6 Expansion, Power Station 5 CCP Project   of GAMA on 24th Aug'2017

Successfully completed COD of Boiler Unit#1 at 2X660 MW Solapur STPP, NTPC, Solapur, Maharashtra on 24th Aug-2017

Successfully Completed Bypass Stack Lifting  in HRSG#12, 1516 MW IBRI Independent Power Project, OMAN of SEPCO-III  on 24th Aug'2017

 

1800 MW First Column Erection Successfully Started at Gama Power Systems, Turkey on 31st July`2017

 

Successfully GTG12 Placement Completed for 1516 MW, TIEJUN,  IBRI Independent Power Project, OMAN on 10th July`2017


 

A) Successfully Completed the Module Erection in HRSG#14 on 03rd July’17

 B) Successfully Completed the HP Drum Erection in HRSG#14 on 08th July’17

 C) Successfully Completed the IP Drum Erection in HRSG#14 on 08th July’17

 D) Successfully Completed LP Drum with Dereator Erection in HRSG#14 on 09th July'17

      1390 MW of Abener Waad Al Shamal ISCC Power Plant,KSA

  A) Successfully GT12 Placement Completed on 10th June`2017

 B) Successfully HRSG#12 Erection Started on 29th June`2017

      1516 MW of SEPCO-III,  IBRI Independent Power Project, OMAN

 Successfully Completed  Boiler  Light Up 660MW Super Critical Thermal  Power Plant of NTPC,   Nabinagar , Bihar on 16th Jul 2017

Successfully Completed Boiler Synchronization of 1X600MW  Rayalaseema Thermal Power Project of APGENCO,  Kadapa, Andhra Pradesh on 02.07.2017

 A) Successfully Completed the Module Erection in HRSG#13 on 02nd June 17

 B) Successfully Completed the HP Drum Erection in HRSG#13 on 13th Jun 17

 C) Successfully Completed the IP Drum Erection in HRSG#13 on 14th Jun 17

 D) Successfully Completed the LP Drum with Dereator Erection in HRSG#13 on 18th Jun 17

 E) Successfully Started the Module Erection in HRSG#14 on 24th  Jun 17

     1390 MW of ABENER, Waad Al Shamal ISCC Power Plant, KSA

Attained Full load of 5X270MW STG, U#5 at BHEL, Nasik TPP, Maharashtra on 30th May 2017

 Successfully completed Trail operation of U#1 at 3x800MW, NTPC Kudgi STPP, Karnataka on 27th May 2017  

Successfully Started the Erection in HRSG#1 of 1516MW, SEPCO-III, IBRI Independent Power Project, OMAN on 24th May 2017

 Successfully Completed the Module, HP Drum, IP Drum & LP Drum   Erection in HRSG#12 and Module Erection in HRSG#13 of  1390MW ABENER, Waad Al Shamal ISCC Power Plant, KSA on 06th,13th &18th of May, 2017

 

 GT&GTG Reliability run test completed of 360MW, L&T, CCPP Development Project, Bheramara on 1st  May’17  and STG Barring Gear completed on 8th May 2017

 